CESC Starts Commercial Operation of 147 MW Solar in Bikaner

CESC's step-down subsidiary Deshraj Solar Energy has put 147 MW of its 150 MW Bikaner solar project into commercial operation.

CESC Bikaner solar: the CESC logo over rows of solar panels under a blue sky

Key Takeaways

  • 147 MW of a 150 MW solar project in Bikaner, Rajasthan, is now in commercial operation.
  • The project belongs to Deshraj Solar Energy, a step-down subsidiary of CESC.
  • The trial run was certified on November 19, 2026, and commercial operation started on November 21.
  • The plant is connected to the Bikaner-III substation of PGCIL.
  • CESC said the remaining 3 MW is expected by January 31, 2027.
Table of Contents 5 sections
  1. CESC's Bikaner solar project at a glance
  2. How the 147 MW got its grid clearance
  3. What CESC said about the last 3 MW
  4. Where CESC's Bikaner plant stands now
  5. FAQs

CESC said in an exchange filing that 147 MW of a 150 MW solar power project in Bikaner, Rajasthan, has started commercial operation. The project belongs to Deshraj Solar Energy Private Limited, a step-down subsidiary of CESC, and the commercial operation date for the 147 MW took effect on November 21, 2026.

The plant is at Karnisar Bhatiyan village in Bikaner district. It is connected to the Bikaner-III substation of Power Grid Corporation of India Limited (PGCIL). The company said the remaining 3 MW is expected to be commissioned by January 31, 2027.

CESC's Bikaner solar project at a glance

DetailValue
CompanyCESC (Kolkata)
Project companyDeshraj Solar Energy Private Limited, a step-down subsidiary of CESC
Total project size150 MW solar
Capacity now in commercial operation147 MW
Commercial operation fromNovember 21, 2026
LocationKarnisar Bhatiyan village, Bikaner district, Rajasthan
Grid connectionBikaner-III substation of PGCIL
Remaining capacity3 MW, expected by January 31, 2027

How the 147 MW got its grid clearance

The 147 MW became operational after a successful trial run. CESC said in its filing that the trial run was certified by Grid Controller of India Limited through its Northern Regional Load Despatch Centre on November 19, 2026. Two days later, on November 21, the commercial operation date for the 147 MW took effect.

The project is linked to the Inter-State Transmission System (ISTS) through the Bikaner-III substation of PGCIL. CESC is a Kolkata-based company, and Deshraj Solar Energy is held by it as a step-down subsidiary.

WhenWhat happened
November 19, 2026Trial run of the 147 MW certified by the Northern Regional Load Despatch Centre of Grid Controller of India
November 21, 2026Commercial operation of 147 MW of the 150 MW project takes effect
By January 31, 2027Remaining 3 MW expected to be commissioned, the company said

What CESC said about the last 3 MW

CESC said the remaining 3 MW of the 150 MW Bikaner project is expected to be commissioned by January 31, 2027.

Where CESC's Bikaner plant stands now

With the commercial operation date in effect, 147 MW of the 150 MW Bikaner solar project is now running for Deshraj Solar Energy. The plant is connected to the Bikaner-III substation of PGCIL. CESC said the last 3 MW is expected to be commissioned by January 31, 2027.

More news

Join Us Add as preferred source
Share

Frequently Asked Questions

What is CESC?

CESC is a Kolkata-based company whose step-down subsidiary, Deshraj Solar Energy, is building a 150 MW solar power project in Bikaner, Rajasthan.

What did CESC announce on November 21, 2026?

CESC said in an exchange filing that 147 MW of its 150 MW solar power project in Bikaner, Rajasthan, has started commercial operation.

How much of CESC's Bikaner solar project is now in commercial operation?

CESC said 147 MW of the 150 MW Bikaner solar project is now in commercial operation.

How big is CESC's Bikaner solar project in total?

CESC's Bikaner solar project has a total size of 150 MW.

How much capacity is still left at CESC's Bikaner project?

CESC said the remaining 3 MW of the Bikaner project is still to be commissioned.

When will CESC commission the remaining 3 MW?

CESC said the remaining 3 MW is expected to be commissioned by January 31, 2027.

How was CESC's 147 MW cleared to start commercial operation?

CESC said the 147 MW became operational after a successful trial run certified by Grid Controller of India Limited through its Northern Regional Load Despatch Centre.

Which CESC company owns the Bikaner solar project?

The Bikaner solar project belongs to Deshraj Solar Energy Private Limited, a step-down subsidiary of CESC.

Where is CESC's Bikaner solar project located?

CESC's solar project is at Karnisar Bhatiyan village in Bikaner district, Rajasthan.

How is CESC's Bikaner solar plant connected to the grid?

CESC's Bikaner solar plant is connected to the Bikaner-III substation of Power Grid Corporation of India Limited.

When did the trial run of CESC's 147 MW get certified?

The trial run of CESC's 147 MW was certified on November 19, 2026, the company said.

From which date is CESC's 147 MW in commercial operation?

CESC's 147 MW at the Bikaner solar project is in commercial operation from November 21, 2026.